Safe isolation of an MCC bucket, in your browser
A motor control centre, or MCC, is a row of cabinets that each feed a motor. Each cabinet has a drawer called a bucket. Before anyone works on the motor or the bucket, it must be isolated safely, in the right order. The free Substation and MCC lab lets you practise that order in a 3D switchroom, in your browser.
The video above shows one full isolation. Here are the steps.
The order matters
Safe isolation is a sequence, and the sequence exists for a reason. If you do a step too early, you can put yourself or others at risk. The lab checks the order for you. If you take a step before you should, it is refused and counted against you, so you learn by feeling the cost of a mistake with nothing real at stake.
Step 1: stop the motor
You start by stopping the motor from its normal control. You never break load by opening an isolator on a running motor, so the first job is to bring the machine to a stop.
Step 2: open the isolator
Once the motor has stopped, you open the isolator so that the bucket is cut off from its supply.
Step 3: withdraw the bucket
Next you withdraw the bucket from the cabinet. This creates a visible, physical gap in the supply, which is stronger than a switch position alone.
Step 4: fit your padlock
You then fit your own padlock so that nobody else can put the supply back while you are working. This is the lock part of lockout and tagout, and it is personal: it stays with the person doing the work.
Step 5: prove dead
Last, you prove that the equipment is dead by testing it. You never assume. You test, then you confirm, and only then is the job safe to start.
Why a 3D switchroom helps
Reading an isolation procedure is easy to forget. Walking through it in a switchroom, with real-style equipment in front of you, makes the sequence stick. It is practice for the procedure, not a replacement for the site rules and training that apply where you work.
Open the Substation and MCC lab and try the isolation yourself. It is free to try.
After isolation
When you are comfortable with this job, move on to the panel lab to practise proving dead with a multimeter on a control panel, and to the PLC lab to see how a motor is started by a program.
See what other learners have finished on the learner wins page.
Practise with us
Internship
Electrical Design
Free internship: 4 weeks, a free certificate and nothing to buy. Premium adds mentor calls and the graded certificate.
See the internshipRoles
Electrical design
Roles that ask for this skill, 72 open in this country now. Free to see and to apply. We are not a recruitment agency.
See rolesTake the free course
Questions
What is an MCC bucket?
It is the withdrawable drawer in a motor control centre that holds the starter for one motor.
What happens if I do a step too early in the lab?
The step is refused and counted against you, so you learn the correct order.
Is the MCC lab free?
Yes, it is free to try and runs in your browser.

Safe Isolation Procedure for Control Panels

Troubleshoot a Control Panel with a Multimeter

Arc Flash PPE Categories 1 to 4: Chart and Methods

NFPA 70E Training Requirements: Who, How Often, 2027

Control Panel Wiring Simulator: Wire a DOL Starter Free Online

Electrical Engineering Work Experience Without an Internship