RAID LOG

RAID Log Example for Engineering Projects

A RAID log keeps risks, assumptions, issues and dependencies in one place. Here is one filled in for an invented pumping station project, with the rules behind each entry.

By EDWartens engineering team 19 October 2026 12 min
RAID Log Example for Engineering Projects

A RAID log is one project record of Risks, Assumptions, Issues and Dependencies. A risk may happen, an issue already has, an assumption is accepted as true until checked, and a dependency is something you need from someone outside the team. This guide fills one in for an invented engineering project, with owners, dates and a sorting rule.

One fact about our own offer, so you can judge this fairly. The EDWartens project coordinator job simulation is a training project at a simulated company, done day by day with project documents, emails and tickets. It is not employment, an internship or a work placement. The first week is free and every ticket is checked as you hand it in. A graded, verifiable certificate is optional, and the longer Premium version is paid; prices show in your own currency before you pay. It shows on your EDWartens profile under Work experience, marked as a job simulation.

RAID in one table

The four letters differ by one question each. Ask the question and the entry sorts itself.

LetterTest questionEngineering exampleUsually owned by
RiskMight this happen in the future?Late delivery of a motor starter could miss the shutdown windowThe person who can reduce it
AssumptionAre we treating this as true without proof?The existing drawings match the equipment on siteThe person who must confirm it
IssueHas it already happened and needs action?The crane hire company has double-booked our liftThe person who can fix it
DependencyDo we need something from someone outside the team?Council approval for a road closureThe person who chases the outside party

A fifth thing sometimes sneaks in: a fact. “The wet well is six metres deep” is information, not an entry. If nothing can change it and nobody needs to act, it belongs in the project brief.

How it differs from other project records

A RAID log is not a risk register, an action log or a change log, although it touches all three. The APM guidance on risk management treats the risk register as its own tool, and many teams keep the two side by side, with the RAID log as the weekly working view. The UK Government project delivery standard is a useful reference for how public-sector projects expect risks, issues and dependencies to be controlled.

RecordWhat it holdsHow it connects
RAID logRisks, assumptions, issues and dependenciesThe weekly working view, feeds the status report
Risk registerRisks only, scored, with responsesDetailed home for risks; RAID entries point to it
Action logTasks with an owner and a dateActions come out of RAID responses
Change logApproved and rejected changes to scope, time or costA change request is raised when a RAID entry needs it

The invented project

The example is an invented refurbishment of the Marlow Down pumping station for a made-up client, Dunmere Water. The work: replace two duty pumps and a standby, fit new actuated valves, replace the motor starters and install a new flow meter. The baseline finishes on the 12th of March, with an agreed shutdown window of three Sundays in January and February. The project coordinator, a role and not a person, keeps the log.

A filled RAID log

Ten entries as they might stand at the end of week six. Each has an ID, a type, a plain description, a named role as owner, a rating or due date, a response and a status. P means probability and I means impact, each scored low, medium or high.

IDTypeDescriptionOwnerRating or dateResponseStatus
R01RiskVariable speed drives may overheat in the existing starter roomLead electrical engineerP medium, I highHeat load check, add a cooling fan if neededOpen
R02RiskSecond pump may fail its performance test, moving the handover dateMechanical leadP low, I highPre-delivery test witnessed at the factoryOpen
R03RiskOperators may ask for a second flow meter late in the projectProject managerP medium, I mediumAgree a deadline for scope requests, route through change controlOpen
A01AssumptionSurvey drawings from 2009 match the installed pipeworkSite engineerConfirm by 20 NovMeasure two key dimensions on the next visitOpen
A02AssumptionOperators can give a shutdown only on SundaysProject coordinatorConfirm by 27 NovWritten confirmation from the client's operations leadOpen
I01IssueActuated valves now due 15 working days later than plannedProcurement leadRaised 2 NovAsk supplier for part shipments, review floatIn progress
I02IssueCrane hire company has double-booked the lift in week 9Site managerRaised 6 NovRebook for the following Sunday, check shutdown windowIn progress
D01DependencyCouncil approval for the road closure for the pump deliveryProject coordinatorNeeded by 4 DecApplication filed; chase weeklyWaiting
D02DependencyUtility confirmation that the supply can carry the new loadLead electrical engineerNeeded by 11 DecMeeting booked with the network operatorWaiting
D03DependencyClient's electrician to disconnect the old starters before the first SundayProject managerNeeded by 10 JanWritten request sent, reply requestedWaiting

Three habits make this log useful. Every entry has one owner, not a team. Every entry has a date, either a rating date or a date by which the thing is needed. And the status line is updated every week, even if it only says “no change, chased 9 Nov”.

A worked example: sort twelve raw comments

At a kick-off workshop twelve comments come up. Try sorting them yourself before reading the answers. They are written as people really talk, which means several fit two boxes until you use the question test.

  1. “The old starter room might not cope with the heat from new drives.”
  2. “We are assuming the existing supply can carry the new pumps.”
  3. “The valve supplier emailed to say delivery is three weeks late.”
  4. “We can't start commissioning until the utility approves the connection.”
  5. “The operator said they might want a second flow meter.”
  6. “We might not get the road closure permit from the council in time.”
  7. “Survey drawings from 2009 are assumed to be accurate.”
  8. “The crane hire company has double-booked the lift.”
  9. “The wet well is six metres deep.”
  10. “Operators say shutdowns can only be on Sundays.”
  11. “We still have no cable pull schedule from the electrical contractor.”
  12. “If the second pump fails its test, the handover could move.”
CommentSorted asReason
1RiskIt may happen; there is no proof yet
2AssumptionTreated as true until the utility confirms
3IssueIt has happened, the notice has arrived
4DependencyNeeds a decision from an outside body
5RiskA possible future change; if it is asked for, it becomes a change request
6DependencyLooks like a risk because of “might”, but the permit comes from an outside party, so it is a dependency with a due date
7AssumptionAccepted without check; needs an owner to verify
8IssueAlready happened
9NoneA fact; put it in the brief
10AssumptionA claim to be confirmed in writing; if confirmed it becomes a constraint
11DependencyWaiting for something from outside the team
12RiskConditional on a future event

Number 6 is the useful one. The word “might” does not make something a risk. Ask who decides. If the answer is someone outside the team, it is a dependency, and the response is to chase, not to mitigate.

When an entry changes type

The log is alive, so entries move. This is the order to follow when one does:

  1. A risk happens: change its type to Issue, keep its ID history, set an owner and a date for the fix.
  2. An assumption is proved wrong: log it as an issue, then ask what else rested on it.
  3. A dependency slips: log an issue for the slip and check the schedule; if it sits on the critical path, tell the project manager that day.
  4. A dependency arrives on time: close it with the date, never delete it.
  5. A risk can no longer happen: close it with the reason and the date.
  6. A scope request arrives: do not do it; record it and raise a change request.

Where an informal scope request goes

The most common leak in an engineering project is a friendly email. A client's operator writes: “Could you also label the old bypass valve while you are there?” It is small, and it is a change. The coordinator's reply is courteous and specific: thank them, state that the request is outside the agreed scope, say it has been logged as a change request with a cost and time estimate to follow, and confirm that nothing will be done until it is approved. Then add a line to the change log and to R03 or a new entry. The kindness is in the speed and the clarity, not in doing the work for free.

From the log to the weekly status report

Once a week the log turns into a one-page report. The key is to write the colour rule before the week starts, so nobody can argue for green under pressure. Here is an example rule for the project above:

ColourRule
GreenForecast finish within 5 working days of baseline, and no high issue without a plan
AmberForecast finish 6 to 15 working days late, or a high issue with a plan not yet proved
RedForecast finish more than 15 working days late, or a high issue with no plan

Apply it to I01. The valves are 15 working days late, but the schedule shows 8 working days of float on that path, so the net slip to the finish is 7 working days. By the rule that is Amber, not Red and not Green. The report says so, shows the response (part shipments) and names the decision the sponsor may need to make. Reporting green because “we will probably catch it up” is the habit that turns a manageable slip into a surprise.

Eight checks before the status report goes out

  • Every open entry has an owner and a date, and none is older than its date without a note.
  • Each issue says what is being done, not only what is wrong.
  • Each dependency says who was chased and when.
  • The colour matches the written rule, not a feeling.
  • Forecast finish is recalculated, not copied from last week.
  • Changes requested this week are listed, with their status.
  • Anything needing a decision names who must decide and by when.
  • Numbers in the report match the log and the schedule.

Practise it in a job simulation

A log like this only becomes natural after you have kept one under pressure. The project coordinator job simulation gives you a project at a simulated company with meetings, emails, a document register and a change request, and each ticket is checked as you hand it in. You can compare it with the site-based roles, such as the substation and motor control centre engineer simulation and the commissioning engineer simulation, to see the same problems from the other side, and the quality engineer simulation shows deviations and changes from a quality view. All are on the job simulation hub.

A finished simulation shows on your EDWartens profile under Work experience, marked as a job simulation, and the optional certificate has a public page where anyone can verify it. For AI in the same job, see our guides on how to use AI in project management and the AI project management internship roadmap, and the matching project management internship track. You can also check current openings on the jobs board.

Last updated 19 October 2026. The project, company and figures in this post are invented. Use your own organisation's templates and scoring scales where they exist.

Practise with us

Internship

SCADA and HMI

Free internship: 4 weeks, a free certificate and nothing to buy. Premium adds mentor calls and the graded certificate.

See the internship

Lab

Process lab

Practise in your browser. Free, nothing to install.

Open the lab (opens in a new tab)

Roles

IIoT and networks

Roles that ask for this skill, 6 open in this country now. Free to see and to apply. We are not a recruitment agency.

See roles

Take the free course

Questions

What does RAID stand for in project management?

Risks, Assumptions, Issues and Dependencies. It is one record that holds the four kinds of thing that can change a plan, so the team sees them together instead of in four separate lists that nobody reads.

Is a RAID log the same as a risk register?

No. A risk register holds only risks, usually with scoring and a response for each. A RAID log adds assumptions, issues and dependencies, so it also shows what has already gone wrong and what the team is waiting for from others. Many projects keep both and link them.

Who owns the RAID log?

The project manager is accountable for it. A project coordinator usually maintains it, chases updates and keeps it tidy. Every entry needs its own named owner, a person who can act on it, because an entry owned by the whole team is owned by nobody.

How often should a RAID log be reviewed?

At least weekly, ahead of the status report, and again before each gate or steering meeting. Fast-moving phases such as commissioning may need a short daily check. A log that is only touched at the start and end of a project is a record, not a tool.

What is the difference between an issue and a risk?

An issue is happening now and needs action. A risk is a possible future event with a probability and an impact. When a risk happens, move it to the issues part and keep the history, including what you did to try to prevent it.

Should a late supplier be a risk or an issue?

Once you have the late notice it is an issue, and it is also a dependency that has slipped. The further delay it might cause, such as a missed shutdown window, is a separate risk. Log both so the response can be different for each.

Do I need Excel or a special tool for a RAID log?

No. A table with the same columns works in a spreadsheet, a shared document or a project tool. Discipline matters more than software: unique IDs, a named owner, a date, a status and a short note on what changed this week.

Can a job simulation help me get a project coordinator job?

It gives you practice with the documents, such as a log, a status report and a change request, with feedback. List it honestly as training or practice at a simulated company, not as employment, and be ready to explain your decisions.

Sources

Written by the EDWartens engineering team for general education. Product names are trademarks of their owners; mentioning them does not imply endorsement. Prices and terms of other providers were checked on the date shown and can change.