A factory acceptance test checklist for a PLC control panel is the ordered list of checks a builder runs and signs before shipping: de-energised checks first, then PLC checks, then staged power, then function tests, fault injection and a sign-off pack. The order matters because you never power a panel you have not checked dead. This guide gives the order, the records to keep and the difference between FAT and SAT. All limits come from your project specification and standards, not from us.
What a factory acceptance test is
A factory acceptance test (FAT) is a structured verification at the builder's premises, before the panel ships, that the build, the wiring, the program and the I/O match the specification. One vendor guide that we read describes it that way, and its phases are the backbone of the order below. Because it is a single vendor's article, treat its numbers as that author's choices and check your own spec.
The test is the moment a customer says "yes, this is what we ordered". Fixing a fault in a workshop is cheaper and quicker than fixing it on site with other trades waiting, which is why FAT is worth doing well.
The RealPars video above shows the first part of a FAT, powering the control panel.
The checklist, phase by phase

Phase 1: de-energised checks on the build
Nothing is powered. This is also where you practise safe working, so lock off any supply that is connected and prove dead before touching terminals; the steps are in our guide to the safe isolation procedure.
- Visual check against the drawings and the bill of materials: right devices, right ratings, right labels.
- Terminal and wire numbering against the schematic.
- Terminal tightness and wire condition.
- Continuity of every circuit and of protective earth bonding.
- Insulation resistance tests where the spec calls for them, with the instrument, the test voltage and the reading recorded. Do this only with the panel isolated, proved dead and the sensitive electronics disconnected as your procedure says.

In EDWartens Lab, the insulation tester can only be used on a locked-out, proven-dead panel, at 500 V or 1000 V. That mirrors the real rule.
Phase 2: PLC checks before power
- Modules seated in the right slots and labelled.
- Program revision and firmware checked against the approved revision, and the backup saved.
- I/O list prepared, with every input and output assigned.
- Force or simulate inputs to prepare the I/O test.
Phase 3: staged energisation
Power goes on in steps so that a fault shows early and small. The vendor guide describes closing the main isolator, then the control supply, then breakers one by one, checking voltages at each stage against tolerances in your spec. Everyone stands clear, the panel door is shut where the design requires it, and a competent person does the work. OSHA's rules on verification, and HSE's preference for dead working, are why Phases 1 and 2 come first.
Phase 4: functional and cause-and-effect tests
Now the panel behaves. For each input, check the PLC sees it. For each output, check it operates the right device. For each sequence, check the order and the timing. A cause-and-effect matrix, where each row is a cause and each column an effect, keeps this tidy and makes sign-off easy.
| Test | Method | Evidence to keep |
|---|---|---|
| Digital inputs | Activate each, check the PLC bit | I/O list ticked |
| Digital outputs | Force each, check the device | I/O list ticked |
| Analogue inputs | Inject a signal, check the scaled value | Value table |
| Start/stop and interlocks | Run the sequence | Signed test sheet |
| Alarms and trips | Trigger each | Alarm log |
| HMI screens | Check each tag and screen | Screenshot set |
Phase 5: fault injection
Prove the panel fails safely. Typical faults the vendor guide lists are a wire break, a short, an overload, phase loss, an interrupted emergency stop chain and loss of communications. For each fault, write the expected response, inject it, and record what happened. A panel that only works when everything is perfect is not accepted.
Phase 6: sign-off pack and punch list
Close with the record. The next section lists what goes in it.
Who does what during a FAT
| Role | Duty |
|---|---|
| Test engineer (builder) | Runs each test, records results, signs sheets |
| Witness (customer or representative) | Observes, challenges, signs to accept |
| Panel builder's quality lead | Controls revisions, calibration records and the punch list |
| Programmer | Supports PLC and HMI tests and fixes software faults |
Agree the roles and the test sheets before the test day. Surprises on the day, such as a missing revision or a missing witness, cost time and credibility. Where the customer asks for changes during the test, log them as variations on the punch list so that the signed record still matches what was built.
Sign-off records to keep
A FAT that is not written down has not happened. The record pack is the product.

Sign-off is by the builder's test engineer and the customer or a representative, who witnesses and accepts. Open points go on a punch list, with owners and dates. The contract decides who can accept and what can be closed after shipping, so confirm that before the test.
Instrument records matter more than people expect. If a reading is challenged later, a calibration date and serial number show the meter could be trusted. Fluke, in a pump-panel case, also suggests re-scanning with a thermal camera after a repair as a complementary check on energised work.
FAT vs SAT

A FAT proves the build and the program in the workshop. A site acceptance test (SAT) proves the installed system works with the real machine, real field devices and real process. A good FAT shortens the SAT, because the same logic, I/O and interlocks have already passed once. We label this a general industry description rather than a figure from a standard; your contract may define both tests differently.
Common reasons a FAT overruns
- The program on the PLC is not the approved revision.
- The I/O list and the drawings disagree, so tests cannot be ticked.
- Test instruments arrive without calibration records.
- Nobody agreed what happens to a failed test, so the argument takes the afternoon.
- The panel is energised before the dead checks are signed.
Each of these is a planning fault, not an engineering one, and each is avoided by agreeing the checklist early.
Standards and limits
IEC 60204-1 covers the electrical equipment of machines from the supply connection onwards. The IEC webstore lists its 6th edition of 2016 consolidated with Amendment 1 of 2021. Another assembly standard, IEC 61439-1, is cited by the vendor guide, but we did not open it, so check it directly if your contract uses it. Check the current editions, because they change.
Test voltages, minimum insulation resistance and voltage tolerances are numbers that come from your standard and project specification. Do not copy a figure from a blog, including this one.
Practise a FAT in the lab
Every job in EDWartens Lab ends in a numbered FAT that runs automatically. In the PLC lab you pass it with a program; in the Panel Lab you pass it after you lock out, prove dead, wire from the schematic and restore power. When you pass, you can download the FAT report as a PDF, and a paid review and signature by a Wartens engineer is available if you want one. The companies in the work orders are fictional, and the lab is a simulation, so it teaches the order and the habit rather than the real hazard.

Try it at lab.edwartens.com or the public pages under /project-sim. It is free with a free EDWartens account, and optional practice in the Free PLC Programming Internship, which is free to join and fully online. It is training, not employment.
Our free courses on control panel design and building, electrical and instrumentation QA/QC inspection, PLC and electrical troubleshooting and Siemens TIA Portal commissioning, simulation and troubleshooting cover the skills behind each phase. For careers, read how to become a commissioning engineer and our post on the electrical QA/QC engineer. Use the FAT report as evidence in a portfolio from course projects. An optional certificate of completion is a paid add-on that anyone can verify at edwartens.com/verification.
Practise for free
Free PLC Programming Internship
Learn, practise and get documents you can verify; no fee to join.
See the internshipTake the free course
FreeElectrical · Beginner · Free
Electrical Control Panel Design, Building and Testing
FreeQuality management · Beginner · Free
Electrical and Instrumentation QA/QC Inspection
FreePLC programming · Beginner · Free
PLC and Electrical Troubleshooting for Maintenance Teams
FreePLC programming · Intermediate · Free
Siemens TIA Portal Commissioning: Hardware, PLCSIM, Backups and Troubleshooting
Questions
What is a factory acceptance test?
A factory acceptance test, or FAT, is a structured check at the builder's premises, before shipping, that a control panel and its program do what the specification and drawings say. It covers the build, the wiring, the PLC program and the I/O, and ends with a signed record that the customer accepts.
What should a FAT checklist for a PLC control panel include?
Visual checks against drawings and the bill of materials, continuity, insulation resistance and earth bonding, PLC module seating and program revision, I/O checks against the I/O list, staged energisation, functional tests, fault injection, and a sign-off pack with instrument calibration dates and a punch list.
What is the difference between FAT and SAT?
A FAT happens at the builder's workshop with the panel on test, before shipping. A site acceptance test, SAT, happens at the customer's site once the panel is installed and connected to the real machine. FAT catches build and program faults early, and SAT proves the installed system works. This split is general industry practice.
Which standards apply to a control panel FAT?
That depends on the contract. IEC 60204-1 covers the electrical equipment of machines, and its 6th edition is dated 2016 with Amendment 1 in 2021. Panel assembly standards such as IEC 61439-1 are also used, and one vendor guide cites both. Always test to the edition and limits named in your project specification.
What insulation test values should I use?
Use the values in your project specification or the standard it names, not a number from a blog. Test voltage and minimum resistance depend on the circuit and the contract, so one vendor's published numbers are one author's choice. Record the instrument, the voltage used and the reading for each circuit.
Who signs off a factory acceptance test?
Usually the panel builder's test engineer signs each test sheet, and the customer or the customer's representative witnesses and signs to accept. The record then lists any open points on a punch list. The contract decides who has authority, so confirm that before the test starts.
Sources
- Industrial Monitor Direct: Factory acceptance test (FAT) procedure for PLC control panels, vendor knowledge base (read 16 October 2026)
- IEC: IEC 60204-1:2016, Safety of machinery, Electrical equipment of machines, with Amendment 1 (2021) (read 16 October 2026)
- HSE: Electricity at work, frequently asked questions (read 16 October 2026)
- OSHA: 29 CFR 1910.333, Selection and use of work practices (read 16 October 2026)
- Fluke: How to troubleshoot a pump control panel (read 16 October 2026)
Written by the EDWartens engineering team for general education. Product names are trademarks of their owners; mentioning them does not imply endorsement. Prices and terms of other providers were checked on the date shown and can change.

How to Become a Freelance Automation Engineer: Skills, Clients and the Business Basics

Internships for Electrical Engineering Students

Data Center Commissioning Levels L1 to L5 Explained

Protection Relay Testing: Types, Procedure and Equipment

Transformer Testing Types: Routine, Type, Special and Field

Troubleshoot a Control Panel with a Multimeter